Microsoft pulls out of Nscale's Essex AI data centre: Tech firm Nscale says it is still committed to building the site in Essex.
bbc.com/news/articles/c9m26kl5y7epo
Microsoft pulls out of Nscale's Essex AI data centre
Microsoft abandons UK AI supercomputer as grid struggles to keep up: Tech giant walks away from flagship Essex project as power connection delays threaten to ...
theregister.com/on-prem/2026/10/19/microsoft-abandons-uk-ai-supercomputer-as-grid-struggles-to-keep-up/5303824
Microsoft abandons UK AI supercomputer as grid struggles to keep up
Microsoft Pulls Out of Giant British AI Cloud Deal Just As Cloud Company Was Expecting to IPO
gizmodo.com/microsoft-pulls-out-of-giant-british-ai-cloud-deal-just-as-cloud-company-was-expecting-to-ipo-2000827469
Microsoft Pulls Out of Giant British AI Cloud Deal Just As Cloud Company ...
Microsoft pulls out of UK data center deal with Nscale, Telegraph reports: Microsoft has pulled out of a data center deal with British cloud ​provider Nscale ...
reuters.com/business/media-telecom/microsoft-pulls-out-uk-data-center-deal-with-nscale-telegraph-reports-2026-10-18/
Microsoft pulls out of UK data center deal with Nscale, Telegraph reports
AI Cloud Firm Nscale Faces Investor Pushback Over IPO Valuation: Nscale Ltd. is facing opposition to the valuation target it’s pursuing in its initial public ...
bloomberg.com/news/articles/2026-10-18/ai-cloud-firm-nscale-faces-investor-pushback-over-ipo-valuation
AI Cloud Firm Nscale Faces Investor Pushback Over IPO Valuation
Microsoft pulls out of AI datacentre project in Essex over power supply concerns: Development by UK firm Nscale heralded by ministers as largest of its kind in ...
theguardian.com/uk-news/2026/oct/18/microsoft-drops-huge-ai-datacentre-project-in-essex-over-power-supply-concerns
Microsoft pulls out of AI datacentre project in Essex over power supply ...
Nscale's Norway data center is six months behind schedule before IPO
dlvr.it/TVy0rn
Nscale's Norway data center is six months behind schedule before IPO
Inside the AI Boom's Arctic Outpost: Above the Arctic Circle, Nscale is turning a remote Norwegian valley into one of Europe’s largest AI data centers.
time.com/article/2026/06/03/ai-norway-nscale-data-center/
Inside the AI Boom's Arctic Outpost
Microsoft takes over OpenAI's Norway Stargate data center
dlvr.it/TS4DyN
Microsoft takes over OpenAI's Norway Stargate data center
Watch Nscale Reaches $14.6 Billion Valuation, Adds Sandberg to Board - Bloomberg: UK data center developer Nscale has become one of Europe's most valuable ...
bloomberg.com/news/videos/2026-03-23/nscale-reaches-14-6b-valuation-adds-sandberg-to-board-video
Watch Nscale Reaches $14.6 Billion Valuation, Adds Sandberg to Board - ...
Invisible datacentres and capricious chips: is UK’s AI bubble about to burst?: Datacentre investment boom is one of the biggest infrastructure gambles of this ...
theguardian.com/news/ng-interactive/2026/mar/14/datacentre-boom-is-uk-ai-bubble-about-to-burst
Invisible datacentres and capricious chips: is UK’s AI bubble about to ...
Nvidia Keeps Minting New Coreweave-Style AI Data Center Unicorns: Nscale, a tiny London-based startup, just landed $500 million in backing from AI chip giant ...
forbes.com/sites/iainmartin/2025/09/22/nvidia-keeps-minting-new-coreweave-style-ai-data-center-unicorns/
Nvidia Keeps Minting New Coreweave-Style AI Data Center Unicorns