News on this topic
Stuttgart 21 - | "Painful and sobering" - | Deutsche Bahn CEO Palla takes stock of Stuttgart 21
stuttgarter-nachrichten.de/inhalt.stuttgart-21-schmerzhaft-und-ernuechternd-bahnchefin-palla-zieht-s-21-bilanz.ff0e6bdb-10b7-4746-8e38-01ed42e13672.html

Stuttgart 21 - | "Painful and sobering" - | CEO Palla takes stock of S-21: The Stuttgart 21 through station will not be completed until 2031 at the earliest ...
stuttgarter-zeitung.de/inhalt.stuttgart-21-schmerzhaft-und-ernuechternd-bahnchefin-palla-zieht-s-21-bilanz.ff0e6bdb-10b7-4746-8e38-01ed42e13672.html

Similar to This
Previous
Stuttgart 21: Stuttgart 21 gets a new CFO: DB CEO Evelyn Palla is continuing to restructure the Stuttgart 21 company; now a managing director with experience in ...
stuttgarter-zeitung.de/lokales/stuttgart/stuttgart-21-stuttgart-21-bekommt-neue-finanzchefin-79395509.html

Paid articlePaywallDeutsche Bahn 2026: Only 59 percent on time – | CEO speaks of “organized irresponsibility”
hna.de/welt/deutsche-bahn-nur-59-prozent-puenktlich-im-ersten-halbjahr-zr-94426950.html

Stuttgart 21: The key statements at the S21 press conference: All those involved in the station project emphasize the new beginning. But Deutsche Bahn CEO Evelyn ...
stuttgarter-zeitung.de/lokales/stuttgart/stuttgart-21-die-schluesselsaetze-bei-der-s21-pressekonferenz-79243569.html

Paid articlePaywallRailway confirms further delay for Stuttgart 21 - | Restrictions for travelers: The Stuttgart 21 railway project will not only cost billions of euros more ...
swr.de/swraktuell/baden-wuerttemberg/stuttgart/s21-lenkungskreis-bahn-eroeffnung-2031-100.html

Key FactsStuttgart 21 Delayed with Rising Costs Confirmed
Jun 26, 2026 · Reading time: ~45 sec.
Summary created with AI assistance · Source: swr.de
Summary created with AI assistance · Source: swr.de
- Deutsche Bahn officially set the Stuttgart 21 launch for December 2031, starting phased openings from 2027.
- Significant planning mistakes and technical challenges caused a €3 billion cost increase, fully borne by the railway company.
- To ease passenger impact, construction sites will be consolidated and replacement bus services will be enhanced.
- Officials demand full completion of all project components, improved transparency, and reduced inconvenience for residents.
The public deserves that we lay everything on the table.— Evelyn Palla, Chairwoman of Deutsche Bahn, said this at the Stuttgart 21 press conference.
Stuttgart 21 - | Railway confirms: Start of S21 postponed to the end of 2031: What we already reported has now been confirmed. Deutsche Bahn is postponing the ...
stuttgarter-zeitung.de/inhalt.stuttgart-21-bahn-bestaetigt-start-von-s21-verschiebt-sich-auf-ende-2031.24f94a48-c22c-4540-ad5a-546e144fa3d3.html

Financial Results: Deutsche Bahn Posts Another Billion-Euro Loss in 2025: Deutsche Bahn posted another billion-euro loss in 2025. While the operating result was ...
zdfheute.de/wirtschaft/unternehmen/bahn-bilanz-milliardenverlust-100.html
Markus Frohnmaier/Lars Haise: AfD Parliamentary Group Demands Inquiry Committee on Stuttgart 21
presseportal.de/pm/130241/6206497

OpinionDeutsche Bahn: How CEO Evelyn Palla is reforming the company: Evelyn Palla has announced rigorous changes. Customers shouldn't expect quick results ...
faz.net/aktuell/wirtschaft/auto-verkehr/deutsche-bahn-wie-bahnchefin-evelyn-palla-den-konzern-reformiert-110809641.html

When will trains finally run through S21? Rail plans to announce the start date in mid-2026
swr.de/swraktuell/baden-wuerttemberg/stuttgart/s21-bahn-sonder-lenkungskreis-sitzung-100.html

Key FactsStuttgart 21 Opening Delayed Until Mid-2026
Dec 15, 2025 · Reading time: ~45 sec.
Summary created with AI assistance · Source: swr.de
Summary created with AI assistance · Source: swr.de
- Project partners agreed to present a new timetable for Stuttgart 21's opening by summer 2026.
- Deutsche Bahn’s CEO Evelyn Palla promised full transparency and assigned 15 staff to investigate the causes of the delays.
- Minister-President Kretschmann stressed the need for a reliable schedule to restore public trust in the project.
- Postponement allows Gäubahn trains to continue using surface tracks longer while financing for the Pfaffensteigtunnel advances.
No one is happy about this situation.— Railway CEO Evelyn Palla commented on the disappointment regarding the delays in the Stuttgart 21 project.
When will Stuttgart 21 open? Project partners discuss postponement: When Stuttgart 21 will go into operation is currently completely unclear ...
stimme.de/baden-wuerttemberg/stuttgart-21-eroeffnung-verschiebung-start-beratung-bahn-projekt-evelyn-palla-art-5122049

Stuttgart 21 - | New Deutsche Bahn CEO Palla meets steering committee for the first time - | What are the results?
stuttgarter-nachrichten.de/inhalt.stuttgart-21-neue-bahnchefin-palla-erstmal-im-lenkungskreis-was-sind-die-ergebnisse.07b1146b-87d3-430d-9086-1dec830db503.html

Stuttgart 21 - | Railway CEO Palla comes to Stuttgart for crisis meeting: After the further postponement of Stuttgart 21, the railway, state, city and region ...
stuttgarter-nachrichten.de/inhalt.stuttgart-21-bahnchefin-palla-kommt-zur-krisensitzung-nach-stuttgart.ec704002-d5d7-468e-a8da-8bdce500d234.html

Stuttgart 21 - Bahnchefin Evelyn Palla wird nach Stuttgart zitiert: Land, Stadt und Region kritisieren die Bahn für die kurzfristige Mitteilung zur erneuten ...
stuttgarter-nachrichten.de/inhalt.stuttgart-21-bahnchefin-evelyn-palla-wird-nach-stuttgart-zitiert.fad55617-7c3a-475d-a862-065a21694d3e.html

“We feel deceived”: S21 opening canceled again.: The partial opening of S21, planned for the end of 2026, is now off the table. No new date has been set ...
schwaebische.de/regional/baden-wuerttemberg/wir-fuehlen-uns-getaeuscht-s21-eroeffnung-schon-wieder-geplatzt-4114995

Schedule scrapped: Deutsche Bahn postpones Stuttgart 21 launch again: Deutsche Bahn has postponed the opening date for Stuttgart 21 – again. Technical problems ...
berliner-zeitung.de/news/bahnchefin-palla-bestaetigt-stuttgart-21-ist-2026-nicht-realisierbar-li.10006376

Key FactsStuttgart 21 Opening Faces Further Delay
Nov 19, 2025 · Reading time: ~45 sec.
Summary created with AI assistance · Source: spiegel.de
Summary created with AI assistance · Source: spiegel.de
- The December 2026 opening of Stuttgart 21 is no longer achievable due to technical setbacks.
- Problems with approval of equipment from Japanese partner Hitachi at the Digital Node Stuttgart cause the delay.
- A new completion date is expected by mid-2026 after a viable plan is developed.
- Project costs have nearly doubled from 4.5 billion to approximately 11 billion euros.
I want to do everything differently at the railway than before.— Evelyn Palla, CEO of the railway, regarding her intention to take a new approach within the company.